Program Wise Bill Status

S.No Program Name No of Scheme Total Sanction Cost Total Work Cost Total Release Amount Release Amount(%)
1 2 3 4 5 6 7
Total 7244 1239449.26 1103167.66 856027.42 77.60%
1 SRDWP 178 43998.69 39067.17 32103.93 82.18%
2 PMJVK 250 64189.11 57011.46 41569.89 72.91%
3 BADP 13 2743.31 2408.14 2354.39 97.77%
4 BUNDELKHAND 7 15709.29 13745.64 13584.77 98.83%
5 I SPARSH 13 2405.13 2104.50 1570.67 74.63%
6 WB-NNP 1 231 48773.24 43134.19 41170.81 95.45%
7 NRDWP:C 4845 777432.62 690657.66 521348.77 75.49%
8 NRDWP:JE 472 113011.53 100747.66 85538.00 84.90%
9 NWQSM 130 28711.46 25601.51 18153.02 70.91%
10 WB-NNP 2 352 125512.09 112713.40 93530.76 82.98%
11 WQMS 603 7272.21 7272.21 4810.17 66.14%
12 SUPPORT 4 527.51 527.51 104.03 19.72%
13 NA 1 6.27 5.57 0.00 0%
14 DMRF 2 8871.80 7886.04 0.00 0%
15 CP UNIT 143 285.00 285.00 188.21 66.04%